FilmLA has gathered the location filming information in this article as a service to the entertainment industry. It is updated regularly, but also subject to change. FilmLA cannot and does not guarantee that the information contained here is at any time complete and without error. By using this site, you acknowledge these limitations and agree that neither FilmLA, nor its predecessors, successors, partners, affiliates, directors, officers, employees, agents or representatives shall be liable for any reason for damages of any nature (including special, incidental, compensatory, consequential or punitive) to any individual or entity who uses or relies on the information contained here for any purpose. Factual errors may be reported to FilmLA using the links provided at the bottom of the article.  

 

 

Standard Requirements

Permit Requirement

In Newport Beach, a temporary use (filming) permit is required for all on-location filming on both public and private property.

 

Application Deadline

10 AM DEADLINE

Application / location submission is due in MyFilmLA by 10 a.m. Late applications are ineligible for processing.

Below are the minimum processing times for permit applications. Holidays may affect deadlines. Changes due to holidays will be posted on our website (www.filmla.com) and sent to registered subscribers via Production Alert, prior to the holiday.  

  • Processing for on-location filming requires a minimum five (5) full business days prior to the first activity date. This does not include the date of submission.
  • All high impact or exceptional activity (example: stunts, special effects, gunfire, aerial activity, closures) will require additional lead time.
  • For example, use of City of Newport Beach personnel extends the application review timeline to ten (10) business days. Please plan accordingly. 

For clarification on deadlines please contract FilmLA's Solution Services department at (213) 977-8600 or info@filmla.com.

 

Standard Filming Hours

Newport Beach maintains strict standard filming hours from 7:00 a.m. to 9:00 p.m. in residential areas. Community Filming Surveys are not an option for extended hours. Filming at areas beaches may begin at 6:00 a.m. pending review by the City. 

 

Insurance Requirements

Filmmakers seeking permits to film on-location in the City of Newport Beach must have insurance on file with FilmLA. If you do not have insurance on file, please provide us with mandatory insurance as per the insurance requirements below.

Insurance coverage limits may vary based on activity and location. We do not advise you to purchase insurance without first discussing your filming plans with a FilmLA insurance specialist.

Please forward all insurance requirements for this jurisdiction to your broker for processing.

Final permits will not be released until all insurance has been reviewed and approved by FilmLA, so please submit your insurance certificates as soon as possible.  

Required Insurance Coverage

  • Commercial General Liability
  • Auto Liability
  • Proof of Workers’ Compensation
     

Minimum Limits (per occurrence)

  • $1,000,000 - Filming / Still Photography
  • $5,000,000 - Aircraft Use
     

Additional Insured

  • The City of Newport Beach added as additional insured; see link below for specific wording and sample.
  • FilmLA must also be added as additional insured; see link below for specific wording and sample.


Insurance Submission

You may submit insurance documentation via MyFilmLA using the file upload link. This upload link can be found in the request email sent to you from the Insurance Department.

If you have any questions about our requirements, please contact our office at 213.977.8600 and ask to speak with an insurance specialist.

Newport Beach Insurance Sample

Newport Beach Hold Harmless Agreement

FilmLA Insurance Sample

 

Department Requirements

Fire Department - Permit to Operate

The City of Newport Beach requires that a form be filled out for the use of candles and open flames, liquid or gas-fueled vehicles or equipment, and erection of tents and membrane structures.

Permit to Operate Form

 

Public Works Department - Street Closures

The City of Newport Beach requires a specific form be filed to temporarily close streets, or portions of streets, for parking and or equipment staging.  

Street Closure Form

 

Parks & Recreation Department - Reservation Requests

The City of Newport Beach requires that all park facilities be reserved not less than five days in advance of planned use. Restrictions on use apply.

Parks & Recreation Reservation Request Form

 

In addition to a valid film permit, the City of Newport Beach requires filmmakers to obtain written use permissions from private property owners.  

Newport Beach Private Property Consent Form

 

Posting / Temporary "no Parking" Signs

Posting requests in Newport Beach must be submitted 5 working days in advance. A production company representative must fill out a separate temporary street closure/use permit application and take it in person to the 1st floor Public Works Counter in Newport Beach at 100 Civic Center Dr. to be reviewed and processed. Direct payment will be made to Newport Beach at this time, and posting signs will be issued. Production is then responsible for posting the ‘No Parking’ signs, 72 hours in advance.

Newport Beach charges a Temporary Street Use permit application fee, plus a per sign fee. Refer to City of Newport Beach’s website for the most up to date fee schedule.

Once ‘No Parking’ signs have been posted, Newport Beach Police Department must verify proper placement.

 

Fee Schedule

 

Common Fees, Newport Beach

FilmLA Basic Fees List

 

Below are the most common fees assessed by this jurisdiction. Additional application, use, or personnel fees may apply based on location or scope of activity for this jurisdiction. Any fees not directly collected by FilmLA on behalf of the municipality through the film permit must be paid directly to the service provider. FilmLA makes every effort to publish the most up to date fees for these municipal service providers, however fees are subject to change at their discretion.

 

 

FilmLA Basic Fees List

Fee Type Rate Per

Permit Application Fee

Up to 5 Locations, 7 Consecutive Days

$931 Permit

Permit Rider Fee

During Business Hours

$148.75 Rider

Permit Rider Fee

After Business Hours

$208 Rider

Still Photo Application Fee*

Cast/Crew of 16+ Requires Motion Rate

$104 Permit
Still Photo Rider Fee $31 Rider
Student Permit Fee (simple) $52 Permit
Student Permit Fee (complex) $134 Permit
Non-Profit (PSA) Permit App Fee $73 Permit
Non-Profit (PSA) Permit Rider Fee $36 Permit

Notification Fee

Base Radius

$232 Radius
Lane Closure Administration Fee $78 Involved Location
Gunfire Administration Fee $78 Involved Location
Special FX - Explosion & Smoke Administration Fee $78 Involved Location
Drone Administration Fee $78 Involved Location
Helicopter Administration Fee $78 Involved Location

FilmLA Monitor Fee**

Minimum Applies. Subject to OT and DT.  Standard Arrival: 1 Hour Prior to Permit Start Time.

$44.50 Hour

* Still photo productions with a cast / crew size of 16 or more people will incur the Motion application fee. Any B-roll or motion filming in conjunction with a still photo shoot will also incur the Motion rate. Additionally, for crews of this size or larger, a LAFD Spot Check Surcharge will also be assessed.

** The FilmLA monitor service is charged in hourly increments based on time at location. For example, if monitor service is required from 6am-10pm, the breakdown of service hours would be 8 Regular hours, 4 overtime hours, and 4 double time hours to cover the service, whether completed by one or multiple monitors.

 

Common Fees, Newport Beach

Fee Type Rate Per

Newport Beach Film Permit Review Fee

6 or More Cast/Crew per Location

$57 Location

Newport Beach Film Permit Review Fee

5 or Fewer Cast/Crew per Location

$13 Location
Newport Beach Police Officer $285.09 Hour
Newport Beach Lifeguards $73.83 Hour

 

 

Community Relations

Community Filming Surveys

The City of Newport Beach does not allow Community Filming Surveys to be used as an option for extended filming hours.

 

Neighborhood Notification

FilmLA's standard notification service satisfies all neighborhood notification requirements for this jurisdiction. Processing notification for on-location filming requires a three day lead time before the first activity. This does not include the date of submission. Please be advised exceptional activity may require more advanced notice. 

 

Special Monitors

When necessary, a FilmLA Monitor will be assigned to an individual production which includes filming that occurs on City-owned property, complicated filming activity and frequently filmed areas, etc. The cost of a Monitor will be billed to the production company.